BHP aims to hold budget line on Jansen Potash expansion

Chamber of Shipping > Blog > News > Local > BHP aims to hold budget line on Jansen Potash expansion

BHP says it will apply lessons from major cost overruns at its Jansen potash project in Saskatchewan to ensure the mine’s second-stage expansion stays closer to budget. Jansen 1’s cost has climbed to as much as $7.4 billion, prompting BHP to push first production to mid-2027 and delay Jansen 2’s start to 2031. The company plans to use modular construction to reduce on-site labour demands and improve productivity, with an updated capital estimate for Stage 2 expected by June 2025. Once fully built, Jansen is set to become one of the world’s largest potash mines, producing 8.5 million tonnes annually. BHP is simultaneously advancing major copper projects in Chile, Argentina, and the US, underscoring its shift toward “future-facing commodities” amid global demand for critical minerals.