Construction on the Trans Mountain Expansion Project has reached a major milestone with more than 50 per cent completion as of March 2022. The halfway mark of construction for the Expansion Project includes more than 412 kilometres of pipe in the ground, 574 kilometres of the pipeline right-of-way stripped and graded, 471 kilometres of pipe welded and the completion of 32 major trenchless crossings.

Since construction began on the Expansion Project, more than 20,000 people have been employed across Alberta and British Columbia. Trans Mountain has negotiated agreements with local governments across BC and Alberta, dedicating more than $16 million to community legacy projects, such as trails and recreational infrastructure improvements, that will have positive and lasting impacts on the lives of thousands of Canadians.